Task Movement within Phases

<< Click to Display Table of Contents >>

RayFlow > 7.4 u1 > User and Administration Guide > Working with RayFlow > Typical User Workflows > Working with Phases 

Task Movement within Phases

A reject event causes the task to be moved to a previous phase. Before setting the reject it is best practice to first enter a comment in the comment section with the reason why the task was rejected.

 

Reject Task to Phase

 

papercliper

Note:

Best Practice means that no package should be allowed to be rejected without a reject reason!